Commercial
& Industrial |
WATKINS Timeline - 411 East 66th Street | ||
Date | Site Photos | Details |
Started Stripping Site and Trenching Sewer Line - looking North | ||
|
||
Setting Blue Tops - N | ||
Setting Blue Tops - W | ||
|
||
Initial Grading - N | Compacting Utility Lines | |
Initial Grading - W | ||
|
||
Grading down to sub-grade - N | North line looking West | |
Grading down to sub-grade - W | Pad looking West | |
|
||
Building up the pad - N | NE Corner | |
Building up the pad - W | SE Corner | |
|
||
Cutting the pad down - N | Cutting the pad - SW corner | |
Cutting the pad down - W | ||
|
||
Preparing Sub-grade - N | Trenching the footings - S | |
Preparing Sub-grade - W | Forming the curb - NW | |
Trenching Utility lines - E | ||
Slab Elevations - SW | ||
|
||
Preparing site concrete work - N | Conc. Footings - W | |
Preparing site concrete work - W | Curb poured - SW | |
Forming the curb - SE | ||
|
||
Started stem-wall forms - N | Finished curb - N | |
Started stem-wall forms - W | Form installation - SW | |
Digging entry drive - S | ||
Compacting Sub-grade - NW truck yard | ||
|
||
Rain | ||
Rain | ||
Rain Go AWAY! | A total of almost 6" of rain fell on the South Plains. | |
|
||
Back to concrete work - N | Installing new electrical service | |
Back to concrete work - W | Working on Stem wall forms - SE | |
Poured East Truck Curb | ||
Finishing East Truck Curb | ||
|
||
More concrete work - N | Laying out steel for 53' Trailer Parking - W | |
More concrete work - W | Pouring concrete for 28' Trailer Parking - W | |
Finishing West Trailer Parking strips | ||
Laying out steel for Concrete Approach | ||
Detail of Dock Edge Channel | ||
Pouring & Vibrating Stem Wall | ||
Detail of Anchor Bolts | ||
Curb off main entry looking NW | ||
|
||
More concrete work - N | Big Projects need Big Tonka Toys | |
Pulled forms off South Stem Wall | ||
Finished West 53' Trailer Parking | ||
Pouring Concrete Approach | ||
Detail of pour for concrete approach - good slump | ||
Finishing work for concrete approach | ||
Corner Detail of Anchor Bolts | ||
Detail showing Dock Edge Channel | ||
|
||
Continue Stem Wall Work - N | Gravel Fill | |
Continue Stem Wall Work - W | Starting 53' Trailer Parking On East Side | |
North Side Stem Wall Steel Layout | ||
Working On East Stem Wall Forms | ||
Detail of South Parking Curb | ||
Detail of Southeast Parking Curb | ||
|
||
Pouring Drive - N | Begin Pouring Drive | |
Pouring Drive - W | Continuing Pouring Drive | |
Finishing Surface of Drive | ||
Finishing Last Stem Wall | ||
Detail for Column and Overhead Door Anchor Bolts | ||
|
||
Backfilling Stem Wall - N | Backfilling Behind Stem Wall | |
Backfilling Stem Wall - W | Compacting Backfill Behind Stem Wall | |
Build Up of Forklift Ramp | ||
View of Compacted Backfill On Northwest Corner | ||
|
||
Utilities Under Slab - N | Formation of Forklift Ramp | |
Utilities Under Slab - W | Stub-Ups For Plumbing | |
Stub-Ups For Electrical | ||
|
||
Rain Delay Again | ||
|
||
Slab Preparation - N | Removing Forms Off of Forklift Ramp | |
Slab Preparation - W | Setting Warehouse Bollards | |
Stub-Ups For Plumbing | ||
Grading Fill For Concrete Apron | ||
|
||
Finishing Aprons - N | Finished East Apron | |
Finishing Aprons - W | Set Bollards Ready For Slab Pour | |
Preparation For West Apron | ||
Applying Rubbed Finish | ||
|
||
Slab Preparation - N | Finished Forklift Ramp | |
Slab Preparation - W | Setting Forms For Handicap Ramp | |
Compacting Sand Fill For Slab | ||
Pouring West Concrete Apron | ||
|
||
After Slab Poured - N | Steel Work For Forklift Landing | |
After Slab Poured - W | Dirt Work For Entry Stair | |
Finishing Handicap Ramp | ||
|
||
Merry Christmas! | ||
|
||
Started Steel Erection - N | Finished Entry Stair and Handicap Ramp | |
Started Steel Erection - W | Finished Forklift Landing | |
Oil Soak For Asphalt Pour | ||
Steel Columns In Place | ||
|
||
Continuing Steel Erection - N | Steel Framing | |
Continuing Steel Erection - W | ||
|
||
Happy New Year! | ||
|
||
Started Laying Asphalt - N | Compacting Asphalt in Passenger Parking Lot | |
Started Laying Asphalt - W | Framing East Overhead Doors | |
Framing West Overhead Doors | ||
|
||
Continuing Steel Work - N | View of Structural System Looking NE | |
Continuing Steel Work - W | ||
|
||
Continuing Laying Asphalt - N | Painted Dock Channel | |
Continuing Laying Asphalt - W | Framing Out Entry Way | |
Laying Asphalt | ||
Laying Asphalt - Dump Truck | ||
|
||
Started Hanging Wall Panels - N | Hanging West Wall Panels | |
Started Hanging Wall Panels - W | Detail of Rubber Closure and Base Trim | |
Hanging Canopy Beam-NW Corner | ||
|
||
Continuation of Wall Panels - N | Hanging East Wall Panels | |
Continuation of Wall Panels- W | Begin Framing Offices | |
Fastening Wall Panel | ||
|
||
Framing Offices - N | Offices Framed Out | |
Framing Offices - W | Hanging West Exit Door | |
Hanging North Exit Door | ||
|
||
Finishing Wall Panels - N | Finished Hanging Wall Panels on West Side | |
Finishing Wall Panels - W | Finished Hanging Wall Panels on Front | |
Finished Hanging Wall Panels on East Side | ||
Begin Hanging Roof Panels | ||
|
||
Beginning Roof Panels - N | Hanging Roof Panels West Side - Interior View | |
Beginning Roof Panels - W | Hanging Roof Panels East Side - Interior View | |
Sky Light Installed | ||
Interior Doors and Windows Framed Out | ||
Hanging Roof Panels West Side - Exterior View | ||
Rolling Roof Panel Seams | ||
|
||
Finishing Roof Panels - N | Front Canopy In Place | |
Finishing Roof Panels - W | Firewall Framed Out | |
Plumbing Installation | ||
Interior View of All Offices | ||
|
||
Started Facia Trim Work - N | Building Forms For Front Concrete Sign | |
Started Facia Trim Work - W | Running Electricity to Front Light Poles | |
Setting Flag Pole Base And Install Facia Trim | ||
Detail of Facia Trim Installation | ||
Adding Supports to Front Canopy | ||
Plumbing Installed Into Each Wall | ||
Begin Installation of Over Head Doors | ||
|
||
Finished Roof Accessories - N | Building Sign On Front Facade | |
Finished Roof Accessories - W | Concrete Sign Base Finished | |
Drainage Channel to Street Complete | ||
Before Roof Ventilators Installed | ||
After Roof Ventilators Installed | ||
Detail of Roof Ventilator Mount | ||
Gutters Installed | ||
Detail of Gutter Mounts | ||
HVAC Unit Installed | ||
Warehouse Fans | ||
|
||
Starting Interior Finish Out - N | Flagpole Erected | |
Starting Interior Finish Out - W | Window Molding Installed | |
Drywall and Ductwork Installed | ||
Plywood and Drywall on Firewall | ||
Light Pole Before Concrete | ||
|
||
Continuing Interior Finish Out - N | Concrete Forms For Light Pole Base | |
Continuing Interior Finish Out - W | Dock Levelers Installed | |
Condensing Unit and Gas Line in Place | ||
Tape and Bed Office Drywall | ||
Plywood Installed in Mechanical Room | ||
Break Room Window Framed Out | ||
Terminal Window Installed | ||
Tape and Bed Firewall | ||
Overall View of Firewall - S | ||
|
||
Continuing Interior Finish Out - N | Entry Way Windows and Doors Finished | |
Continuing Interior Finish Out - W | Offices Painted | |
Electrical Service Panels Installed | ||
|
||
Continuing Interior Finish Out - N | Wiring Service Panels | |
Continuing Interior Finish Out - W | Beginning Ceiling Grid Installation | |
Terminal Mgr. Interior Window Finished | ||
Dispatch Window Finished | ||
Fans Installed in Terminal | ||
Bollards Capped and Welded | ||
|
||
Continuing Interior Finish Out - N | Trench For Telephone | |
Continuing Interior Finish Out - W | Concrete Sign In Place | |
Trees Planted and Light Pole Bases Set | ||
Detail of Light Pole Base | ||
Detail of Entry Way Steps | ||
Ceiling Grid Padded Out | ||
Storage Shelves Started | ||
Water Fountain and Wainscot Installed | ||
Plumbing Fixtures Installed | ||
Water Heater and Mop Sink Installed | ||
Finished Window in Dispatch Room | ||
Started Painting Bollards | ||
|
||
Continuing Site Work - N | Stub-up For Concrete Sign Lighting | |
Continuing Site Work - W | Sprinkler System Installed | |
Detail of Sprinkler Head | ||
Rubbed Finish Applied to Light Pole Base | ||
Fence Poles Ready to be Set | ||
Fabricating Steel Railing | ||
Begin Handicap Rail | ||
Stairway By Forklift Ramp In Place | ||
Stairway By North Door In Place | ||
Installing Wall Panels For Below Eve Canopy | ||
Finishing Shelving In Dispatch Room | ||
Doors Hung | ||
Installing Floor Outlet | ||
|
||
Continuing Interior Finish Out - N | Front Fence Poles Ready to be Set | |
Continuing Interior Finish Out - W | Hidden Gutter in Canopy Installed | |
Floor Tile Installed | ||
Telephone System Installed | ||
Finished Cabinets In Break Room | ||
Bill Boxes Installed | ||
Dock Lights Installed | ||
|
||
Move In Date - N | Front Gate Installed | |
Move In Date - W | Curb Poured For Cantilevered Gate | |
Pedestrian Gate Installed | ||
Railing Installed On Forklift Ramp and Landing | ||
Exterior Building Lighting Installed | ||
Fencing and Light Poles Installed | ||
Office Furniture Installed | ||
Shelving Cubicles Complete in Dispatch Room | ||
Warehouse Lights and Door Signs In Place | ||
Copyright 1999-2002, Wilkerson Properties, Inc. |