z   

Commercial & Industrial
Development, Management, & Brokerage

Lubbock, Texas
Phone: (806) 745-3611        Fax: (806) 474-2216

 


3d Photographic Rendering

Renderings  SW view Signage NW view

City Bank Branch at Idalou
Date

Site Photos

Details


12-10-07

NW overall Progress of future sonic Furniture in vestibule View toward teller counter View toward teller counter View toward waiting area Furniture in typical office Installation of day gate Waiting area furniture Waiting area side of fireplace Branch manager side of fireplace Branch manager - Bob Cosby

Opening day!


11-19-07

NW view SW view SE view

Exterior night shots


11-09-07

Added logo to main entry sign Prep work for left turn lane Prep work for left turn lane Finished all carpet/flooring Installed floor outlet covers Installed baseboard & blinds Installed blinds Detail of baseboard @ interior radius Detail of baseboard @ exterior radius Finished elevation @ teller counter All interior glass installed Wiring @ tele/computer room

Finished flooring, base, glass, & blinds


11-07-07

Started highway turn lane Caulked all site joints Drive-thru striping & arrows Handicap striping & signs Parking lot striping SE entry/exit arrows Exit arrows/striping

Started highway turn lane/Finished site striping 


10-31-07

Patched S street w/ asphalt Granite for teller counter installed Detail of granite @ teller counter Overall of granite @ check counter/internet station Detail of granite @ check counter Carpet in manager's office Carpet in main lobby Detail of granite cap behind teller counter   VCT installed in break room

Granite counter tops/Flooring installed


10-25-07

Ceiling grid above drive-thru padded out Installation of security camera Security camera installed @ drive-thru column Security camera installed @ W side of building Ceiling grid padded out Ceiling grid padded out Ceiling grided padded out Computer room shelves  Sink & Ice maker installe Teller counter equipment wiring

Ceiling grids padded out/Security cameras installed


10-17-07

Monument sign Monument sign connection City Bank signage Signage @ drive-thru ATM signage installed Traffic control signage @ drive thru lanes Vacuum tubes installed @ drive-thru ATM installed A/C units installed

Landscaping/Interior details


10-09-07

SE island landscaping SE building landscaping Main entry landscaping Landscaping @ flagpoles Ceiling grid completed @ drive-thru Detqil of blower motors Ceiling grid, lighting, & grilles in main lobby area Started installing fixtures in men's restroom Started installing fixtures in women's restroom Millwork in break room Millwork in tele./comp. room Millwork @ teller counter

Landscaping/Interior details


10-03-07

Sod placed in ROW Sod placed @ E side Sod @ main entry Light poles installed VAT tubes @ drive-thru Ceiling grid & VAT tubes @ drive-thru Ceramic tile in vestibule Ceramic tile in main lobby Door, window frames/trim installed Ceiling grid, grilles, and lighting Vaccume tubing installed @ teller window Ceramic tile in restrooms Ceramic tile on fireplace Check/internet station Millwork Millwork @ teller counter

Misc. details


09-18-07

Downspouts installed Detail of downspouts Framing of drive-thru islands Assembling of canopies Canopies installed Canopy connection detail Installed cover plates over trench drain Light poles prior to installation Ground lighting at main entrance Elec. conduits for sprinkler system Mudding windows Mudding windows at corners Tapping/mudding at SE corner Wiring elec. panel

Started tapping/mudding on walls


09-13-07

NW view Installation of gutters Installation of gutters Started forming of drive-thru islands Drywall installed in vestibule Insulation/drywall in managers office Drywall above teller counter Drywall at SE corner Drywall behind teller counter Drywall in files room Drywall in break room Drywall ceilings in restrooms Telephone/data wiring pulled Installed access panel for water cut off

Continued drywall/installation of gutters


09-07-07

SE view of drive-thru S view of drive-thru Finished CMU at drive-thru Installation of gutters Installation of gutters Drywall at branch managers office Drywall at N wall Break room view toward coat closet Drywall at teller window Framing for access hatch

Finished CMU at drive-thru/continued drywall


08-28-07

Started trenching for sprinkler system Started trenching for sprinkler system Sheathing completed at drive-thru S view of drive-thru View of uncrimped VSR panel Fireplace delivered Plywood walls/Dry wall ceiling in restrooms Started plywood in restrooms Started dry wall installation Started insulation & drywall

Started insulation & drywall


08-23-07

Finished framing at drive-thru canopy Sheathing around drive-thru columns Started sheathing at drive-thru canopy Started moduleze soffit panels Elec. J-boxes for sconces in vestibule 3/4 vestibule roof panels installed Framing for fur down above teller counter Elec. J-boxes for ceiling lights Finished roofing in cricket Restroom vent pipes Plumbing/blocking in restrooms

Started sheathing at drive-thru


08-21-07

NE view N view NW view Drive-thru canopy Poured concrete flagpole bases Electrical panel Blocking/hangers for plumbing fixtures Blocking for cabinets Floor drain installed in restrooms Air handlers placed above decked area Installing duct work Installing duct work Installing duct work 2x4 blocking around doors and windows

Misc. details


08-17-07

SW view Installation of roof panels at drive-thru Poured light pole bases Setting of bollards Wall framing continued Wall framing inside vestibule Plywood decking above janitor's closet Electrical boxes at teller window

Continued interior wall framing


08-14-07

NW view Staking for main signage Rebar for light pole base Poured slab for A/C unit Interior vestibule entry Wall framing around restrooms Electrical boxes installed Framing for light fixtures in restrooms Framing for decking above break room

Continued interior wall framing


08-08-07

Installing roof panels Installing roof panels Diebold teller window installed Exterior of transaction drawer Metal edging around trees placed Safety end treatment of culvert poured Hole for light pole base Interior of transaction drawer Interior looking up at roof panels Started framing interior walls

Started roof panel installation


08-03-07

NE view Main entry Side entry glass Typ. window Header mulls installed at teller window Main truss system Drive-thru truss system W view

Installed all windows & entry glass


08-01-07

Poured main drive Concrete paving at shared drive Installing trusses at drive-thru Concrete pad for A/C units

Misc. site concrete & steel erection details


07-30-07

Erection of structural steel at drive-thru Forms & rebar at the main drive

Misc. site concrete & steel erection details


07-27-07

Dumpster & transformer pads Forming for main drive Staking of North island Staking of West paving line Installation of intermediate support tube & angle Continuing installation of bracing & hat channel Installing edge conditions

Misc. details


07-23-07

Drainage culvert for main drive Landscape island for main drive. NW overall NE overall Connection of roof system at vestibule

Continued erection of Skyline truss system


07-17-07

Perimeter sidewalks completed

Started erection of Skyline truss system


07-13-07

NE view NW view Drive-thru structure Drive-thru structure Drive-thru structure Vestibule lintel Vestibule lintel

Misc. details


07-09-07

Rain delay-9th


07-06-07

Planting of trees


07-03-07

Pouring site paving & finished CMU


06-26-07

Embed plates in bond beam Setting anchor bolts for drive-thru columns

Site details


06-19-07

Curb & gutter/sidewalk details


06-14-07

Trench drain installed Anchor bolts for drive-thru columns

Site details


06-10-07

Rain delay-10th


06-01-07

Rain delay-1st - 3rd

1.74 inches


05-31-07

Glass block detail South curb & gutter Temporary power

Site details


05-24-07

Delivery of Skyline system Delivery of Skyline system Frame for personnel door Rough opening for night depository Rough opening for teller window

Site details


05-22-07

Delivery of CMU block Tied rebar at entrances

Forming of driveway 


05-17-07

Rain delay-17th & 18th


05-15-07

Setting curb & gutter forms Setting curb & gutter forms Hose bib & sprinkler system  

Pouring the slab


05-08-07

Rain delay-8th & 9th

2 inches


05-07-07

Rebar cages for footings

Site details


05-02-07

Rain delay-2nd


05-01-07

Power lines Electrical trench Primary power Trench for footings Trenching for footings Plumbing stub-ups Trench for water main Water tap by city of Idalou

Site trenching


Fourth week in April

Trenching for sewer to restrooms Gas line trench Trenching of gas and water lines Stub-ups for restrooms Stub-ups for restrooms

Site trenching


Third week in April

Location of existing sewer line  Set batter boards for building corners

Site details


04-18-07

Site flooded


04-17-07

Rain delay-17th


04-15-07

Marking of gas line Marking of gas line

Grading of site


04-13-07

Rain delay-13th


04-10-07

Site work delayed due to rain


04-07-07

Rain & snow delay-7th

2.03 Inches of rain/snow


First week in April

Removal of  existing trees  

Grading of site-official start date April 2, 2007


Month of March

Rain delay

+6 Inches


03-01-07

Presentation of  Future City Bank Idalou Bob Cosby-City Bank branch manager Curtis Griffith-City Bank Chairmen of the Board  City of Idalou Officials Attendees at ground breaking

Ground Breaking ceremony


Copyright 1999-2007, Wilkerson Properties, Inc.
For problems or questions regarding this web contact webmaster@wilkersonproperties.com.
Last updated: December 11, 2007