City Bank Branch at Idalou | |||
Date |
Site Photos |
Details |
|
|
|||
12-10-07 |
Opening day! |
||
|
|||
11-19-07 |
Exterior night shots |
||
|
|||
11-09-07 |
Finished flooring, base, glass, & blinds |
||
|
|||
11-07-07 |
Started highway turn lane/Finished site striping |
||
|
|||
10-31-07 |
Granite counter tops/Flooring installed |
||
|
|||
10-25-07 |
Ceiling grids padded out/Security cameras installed |
||
|
|||
10-17-07 |
Landscaping/Interior details |
||
|
|||
10-09-07 |
Landscaping/Interior details |
||
|
|||
10-03-07 |
Misc. details |
||
|
|||
09-18-07 |
Started tapping/mudding on walls |
||
|
|||
09-13-07 |
Continued drywall/installation of gutters |
||
|
|||
09-07-07 |
Finished CMU at drive-thru/continued drywall |
||
|
|||
08-28-07 |
Started insulation & drywall |
||
|
|||
08-23-07 |
Started sheathing at drive-thru |
||
|
|||
08-21-07 |
Misc. details |
||
|
|||
08-17-07 |
Continued interior wall framing |
||
|
|||
08-14-07 |
Continued interior wall framing |
||
|
|||
08-08-07 |
Started roof panel installation |
||
|
|||
08-03-07 |
Installed all windows & entry glass |
||
|
|||
08-01-07 |
Misc. site concrete & steel erection details |
||
|
|||
07-30-07 |
Misc. site concrete & steel erection details |
||
|
|||
07-27-07 |
Misc. details |
||
|
|||
07-23-07 |
Continued erection of Skyline truss system |
||
|
|||
07-17-07 |
Started erection of Skyline truss system |
||
|
|||
07-13-07 |
Misc. details |
||
|
|||
07-09-07 |
|
|
|
|
|||
07-06-07 |
Planting of trees |
||
|
|||
07-03-07 |
Pouring site paving & finished CMU |
||
|
|||
06-26-07 |
Site details |
||
|
|||
06-19-07 |
Curb & gutter/sidewalk details |
||
|
|||
06-14-07 |
Site details |
||
|
|||
06-10-07 |
|
|
|
|
|||
06-01-07 |
|
1.74 inches |
|
|
|||
05-31-07 |
Site details |
||
|
|||
05-24-07 |
Site details |
||
|
|||
05-22-07 |
Forming of driveway |
||
|
|||
05-17-07 |
|
||
|
|||
05-15-07 |
Pouring the slab |
||
|
|||
05-08-07 |
|
2 inches |
|
|
|||
05-07-07 |
Site details |
||
|
|||
05-02-07 |
|
|
|
|
|||
05-01-07 |
Site trenching |
||
|
|||
Fourth week in April |
Site trenching |
||
|
|||
Third week in April |
Site details |
||
|
|||
04-18-07 |
Site flooded |
||
|
|||
04-17-07 |
|
|
|
|
|||
04-15-07 |
Grading of site |
||
|
|||
04-13-07 |
|
|
|
|
|||
04-10-07 |
Site work delayed due to rain |
||
|
|||
04-07-07 |
|
2.03 Inches of rain/snow |
|
|
|||
First week in April |
Grading of site-official start date April 2, 2007 |
||
|
|||
Month of March |
|
+6 Inches |
|
|
|||
03-01-07 |
Ground Breaking ceremony |
||
|
|||