City Bank Branch at 5506 4th Street | |||
Date | Site Photos | Details | |
|
|||
04-17-07 |
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Completed exterior details | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Interior details | ||
|
|||
03-19-07 |
![]() ![]() ![]() ![]() ![]() ![]() |
Exterior details | |
|
|||
03-11-07 |
![]() |
2.63 Inches | |
|
|||
02-28-07 |
![]() ![]() ![]() ![]() ![]() ![]() |
EIFS application | |
![]() ![]() ![]() ![]() |
Interior details | ||
|
|||
02-24-07 |
![]() |
Sustained winds at 56 m.p.h. w/ gusts of 64 m.p.h. | |
|
|||
02-19-07 |
![]() ![]() ![]() ![]() ![]() |
Scratch coat application for EIFS | |
![]() ![]() ![]() ![]() ![]() |
Interior details | ||
![]() ![]() ![]() ![]() |
Millwork details | ||
|
|||
02-14-07 |
![]() ![]() |
2.36 inches | |
|
|||
02-06-07 |
![]() ![]() ![]() ![]() ![]() |
Exterior details | |
![]() ![]() ![]() ![]() |
Foam application | ||
![]() ![]() ![]() ![]() |
Interior details | ||
![]() ![]() ![]() |
Millwork details | ||
|
|||
02-01-07 |
![]() ![]() |
2.8 inches | |
|
|||
01-30-07 |
![]() ![]() ![]() ![]() ![]() ![]() |
Stone application | |
![]() ![]() ![]() ![]() |
Foam application | ||
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Roof details | ||
![]() ![]() ![]() ![]() |
Interior details | ||
![]() ![]() ![]() ![]() ![]() |
Installation of millwork | ||
|
|||
01-25-07 |
![]() ![]() ![]() ![]() ![]() |
Preparation for EIFS application | |
![]() ![]() ![]() |
Drive-thru roof installation | ||
![]() ![]() ![]() ![]() ![]() ![]() |
Painting interior | ||
![]() ![]() ![]() ![]() |
Installation of millwork | ||
|
|||
01-22-07 |
![]() ![]() ![]() ![]() |
Canopy and ledger angle details | |
|
|||
01-19-07 |
![]() ![]() |
1.7 inches of rain/sleet, 4.3 inches of snow | |
|
|||
01-16-07 |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Exterior details | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Interior finish out | ||
|
|||
01-10-07 |
![]() ![]() ![]() ![]() ![]() ![]() |
Exterior details | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Interior finish out | ||
|
|||
01-04-07 |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
Exterior elevations | |
![]() ![]() ![]() ![]() ![]() |
Vestibule details | ||
![]() ![]() ![]() ![]() |
Misc. interior details | ||
|
|||
12-29-06 |
![]() |
||
|
|||
12-21-06 |
![]() ![]() ![]() ![]() ![]() |
Exterior elevations | |
![]() ![]() ![]() ![]() ![]() |
Started interior framing | ||
![]() ![]() |
Misc. interior details | ||
|
|
||
12-19-06 |
![]() ![]() |
1 inch | |
|
|||
12-18-06 |
![]() ![]() ![]() |
Begin cutting out openings | |
![]() ![]() ![]() ![]() ![]() |
Window and door openings | ||
![]() ![]() |
Tracks for stud walls | ||
|
|||
12-12-06 |
![]() ![]() ![]() ![]() ![]() ![]() |
Installation of Koreteck | |
|
|||
12-06-06 |
![]() ![]() |
Arrival of Koreteck panels | |
![]() ![]() ![]() |
Site prep for Koreteck | ||
|
|||
11-30-06 |
![]() |
3 inches | |
|
|||
11-28-06 |
![]() ![]() ![]() |
Misc. site details | |
![]() ![]() |
Set bollards in islands | ||
![]() ![]() ![]() ![]() |
Continued structural erection | ||
|
|||
11-22-06 |
![]() ![]() |
Misc. site details | |
![]() ![]() |
Erecting structural framing | ||
|
|||
11-20-06 |
![]() ![]() |
Footings | |
![]() |
Sidewalk prep | ||
|
|||
11-14-06 |
![]() ![]() ![]() ![]() ![]() |
Concrete paving of site | |
|
|||
11-03-06 |
![]() |
Poured curb at drive thru exit | |
![]() ![]() ![]() |
Slab poured and covered | ||
|
|||
11-05-06 |
![]() ![]() ![]() |
Retrenched all footings due to rain delay | |
![]() |
Site prep for drive thru area | ||
|
|||
10-15-06 |
![]() |
||
|
|||
10-08-06 |
![]() |
||
|
|||
10-05-06 |
![]() |
Water meters | |
![]() |
Electrical stub ups | ||
|
|||
10-03-06 |
![]() ![]() ![]() ![]() ![]() ![]() |
Stub ups for plumbing and electrical | |
![]() |
Railing and valley gutter at retaining wall | ||
|
|||
9-19-06 |
![]() |
Trenching for footings | |
![]() ![]() |
Laying plumbing | ||
![]() ![]() |
Forming footings | ||
|
|||
9-10-06 |
![]() |
||
|
|||
9-01-06 |
![]() |
||
|
|||
8-26-06 |
![]() |
||
|
|||
8-25-06 |
![]() ![]() ![]() |
Retaining wall | |
![]() ![]() |
Layout for electrical trenching | ||
![]() |
Rebar mats for slab | ||
|
|||
8-19-06 |
![]() |
||
|
|||
8-18-06 |
![]() |
Cutout for West curb | |
![]() ![]() ![]() |
Forming of footings | ||
|
|||
8-14-06 |
![]() |
||
|
|||
8-08-06 |
![]() |
Forming upper retaining wall | |
![]() ![]() |
Marking building corners | ||
|
|||
7-28-06 |
![]() |
||
|
|||
7-27-06 |
![]() ![]() |
Backfilled behind retaining wall | |
|
|||
7-24-06 |
![]() ![]() ![]() ![]() ![]() |
Forming and pouring 1st section of retaining wall | |
|
|||
6-29-06 |
![]() ![]() ![]() |
Digging drive & placing erosion control | |
|
|||
1-27-06 |
![]() ![]() ![]() ![]() |
Initial survey of proposed site | |
|
|||