City Bank Branch at 5506 4th Street | |||
Date | Site Photos | Details | |
|
|||
04-17-07 |
Completed exterior details | ||
Interior details | |||
|
|||
03-19-07 |
Exterior details | ||
|
|||
03-11-07 |
Rain delay-11th-12th | 2.63 Inches | |
|
|||
02-28-07 |
EIFS application | ||
Interior details | |||
|
|||
02-24-07 |
Dust storm-24th | Sustained winds at 56 m.p.h. w/ gusts of 64 m.p.h. | |
|
|||
02-19-07 |
Scratch coat application for EIFS | ||
Interior details | |||
Millwork details | |||
|
|||
02-14-07 |
Rain & snow delay-14th | 2.36 inches | |
|
|||
02-06-07 |
Exterior details | ||
Foam application | |||
Interior details | |||
Millwork details | |||
|
|||
02-01-07 |
Rain & snow delay-1st & 2nd | 2.8 inches | |
|
|||
01-30-07 |
Stone application | ||
Foam application | |||
Roof details | |||
Interior details | |||
Installation of millwork | |||
|
|||
01-25-07 |
Preparation for EIFS application | ||
Drive-thru roof installation | |||
Painting interior | |||
Installation of millwork | |||
|
|||
01-22-07 |
Canopy and ledger angle details | ||
|
|||
01-19-07 |
Rain & snow delay-19th & 20th | 1.7 inches of rain/sleet, 4.3 inches of snow | |
|
|||
01-16-07 |
Exterior details | ||
Interior finish out | |||
|
|||
01-10-07 |
Exterior details | ||
Interior finish out | |||
|
|||
01-04-07 |
Exterior elevations | ||
Vestibule details | |||
Misc. interior details | |||
|
|||
12-29-06 |
Rain delay 29th | ||
|
|||
12-21-06 |
Exterior elevations | ||
Started interior framing | |||
Misc. interior details | |||
|
|
||
12-19-06 |
Rain & snow delay-19th & 20th | 1 inch | |
|
|||
12-18-06 |
Begin cutting out openings | ||
Window and door openings | |||
Tracks for stud walls | |||
|
|||
12-12-06 |
Installation of Koreteck | ||
|
|||
12-06-06 |
Arrival of Koreteck panels | ||
Site prep for Koreteck | |||
|
|||
11-30-06 |
Snow delay 30th | 3 inches | |
|
|||
11-28-06 |
Misc. site details | ||
Set bollards in islands | |||
Continued structural erection | |||
|
|||
11-22-06 |
Misc. site details | ||
Erecting structural framing | |||
|
|||
11-20-06 |
Footings | ||
Sidewalk prep | |||
|
|||
11-14-06 |
Concrete paving of site | ||
|
|||
11-03-06 |
Poured curb at drive thru exit | ||
Slab poured and covered | |||
|
|||
11-05-06 |
Retrenched all footings due to rain delay | ||
Site prep for drive thru area | |||
|
|||
10-15-06 |
Rain delay 15th | ||
|
|||
10-08-06 |
Rain delay 8th-10th | ||
|
|||
10-05-06 |
Water meters | ||
Electrical stub ups | |||
|
|||
10-03-06 |
Stub ups for plumbing and electrical | ||
Railing and valley gutter at retaining wall | |||
|
|||
9-19-06 |
Trenching for footings | ||
Laying plumbing | |||
Forming footings | |||
|
|||
9-10-06 |
Rain delay 10th-13th | ||
|
|||
9-01-06 |
Rain delay 1st-4th | ||
|
|||
8-26-06 |
Rain delay 26th-28th | ||
|
|||
8-25-06 |
Retaining wall | ||
Layout for electrical trenching | |||
Rebar mats for slab | |||
|
|||
8-19-06 |
Rain delay 19th-21st | ||
|
|||
8-18-06 |
Cutout for West curb | ||
Forming of footings | |||
|
|||
8-14-06 |
Rain delay 14th-16th | ||
|
|||
8-08-06 |
Forming upper retaining wall | ||
Marking building corners | |||
|
|||
7-28-06 |
Rain delay | ||
|
|||
7-27-06 |
Backfilled behind retaining wall | ||
|
|||
7-24-06 |
Forming and pouring 1st section of retaining wall | ||
|
|||
6-29-06 |
Digging drive & placing erosion control | ||
|
|||
1-27-06 |
Initial survey of proposed site | ||
|
|||